Abstract:
The bridge construction industry in Sri Lanka has been severely affected by the time
overrun events in the past. The trend is continuing and the requirement of taking mitigation
measures in the industry is a high priority. Once a time overrun event occurs, it will be
analysed by the consultant of the contract. If the accountability of it is on the client, the
contractor will be granted an Extension of Time and the relevant compensations.
Therefore, identifying the causes of the time overrun events and the accountable party of
those is a high necessity for forecasting and taking mitigation measures.
The research is on identifying the key time overrun events accountable to the client in
bridge construction projects, Sri Lanka. Seventy (70) time overrun events in bridge
construction projects have been found by literature review and case studies of 18 projects.
These time overrun events are analysed from the responses by the professionals through a
questionnaire survey and found out nineteen (19) time overrun events accountable to the
client using the Relative Importance Index. The analyses have been continued through
interviews with the key experts of the field as well to understand the probability and impact
of the events. Accordingly, by using the Frequency Index and Severity Index, the events
were prioritized and the use of Probability-Impact Matrix, it has been identified the five
(5) most critical events accountable to the client in the bridge construction projects which
are Possession of site, Unclear scope (Variation Orders), Land acquisition matters, Utility
shifting matters and Design changes.
Further, it has been observed that around 70% of time overrun events accountable to the
client can be forecasted in the planning phase (before awarding the contract) of the project.
Therefore, the research recommends several methods for conducting a proper planning
phase of a project by highlighting the current drawbacks and hence avoiding or mitigating
the risk of time overrun events that would be generated during the construction phase of
the project.
Citation:
Lakshamana, N.W.H. (2022). Time overrun events accountable to the client in bridge construction projects, Sri Lanka [Master's theses, University of Moratuwa]. Institutional Repository University of Moratuwa. http://dl.lib.uom.lk/handle/123/21616