Institutional-Repository, University of Moratuwa.  

Time overrun events accountable to the client in bridge construction projects, Sri Lanka

Show simple item record

dc.contributor.advisor Siriwardana C
dc.contributor.author Lakshamana NWH
dc.date.accessioned 2022
dc.date.available 2022
dc.date.issued 2022
dc.identifier.citation Lakshamana, N.W.H. (2022). Time overrun events accountable to the client in bridge construction projects, Sri Lanka [Master's theses, University of Moratuwa]. Institutional Repository University of Moratuwa. http://dl.lib.uom.lk/handle/123/21616
dc.identifier.uri http://dl.lib.uom.lk/handle/123/21616
dc.description.abstract The bridge construction industry in Sri Lanka has been severely affected by the time overrun events in the past. The trend is continuing and the requirement of taking mitigation measures in the industry is a high priority. Once a time overrun event occurs, it will be analysed by the consultant of the contract. If the accountability of it is on the client, the contractor will be granted an Extension of Time and the relevant compensations. Therefore, identifying the causes of the time overrun events and the accountable party of those is a high necessity for forecasting and taking mitigation measures. The research is on identifying the key time overrun events accountable to the client in bridge construction projects, Sri Lanka. Seventy (70) time overrun events in bridge construction projects have been found by literature review and case studies of 18 projects. These time overrun events are analysed from the responses by the professionals through a questionnaire survey and found out nineteen (19) time overrun events accountable to the client using the Relative Importance Index. The analyses have been continued through interviews with the key experts of the field as well to understand the probability and impact of the events. Accordingly, by using the Frequency Index and Severity Index, the events were prioritized and the use of Probability-Impact Matrix, it has been identified the five (5) most critical events accountable to the client in the bridge construction projects which are Possession of site, Unclear scope (Variation Orders), Land acquisition matters, Utility shifting matters and Design changes. Further, it has been observed that around 70% of time overrun events accountable to the client can be forecasted in the planning phase (before awarding the contract) of the project. Therefore, the research recommends several methods for conducting a proper planning phase of a project by highlighting the current drawbacks and hence avoiding or mitigating the risk of time overrun events that would be generated during the construction phase of the project. en_US
dc.language.iso en en_US
dc.subject TIME OVERRUN en_US
dc.subject ACCOUNTABILITY en_US
dc.subject CLIENT en_US
dc.subject MITIGATION MEASURES en_US
dc.subject RELATIVEIMPORTANCE INDEX en_US
dc.subject CONSTRUCTION COMPANIES - Sri Lanka en_US
dc.subject BRIDGE CONSTRUCTION en_US
dc.subject CIVIL ENGINEERING -Dissertation en_US
dc.subject CONSTRUCTION PROJECT MANAGEMENT- Dissertation en_US
dc.title Time overrun events accountable to the client in bridge construction projects, Sri Lanka en_US
dc.type Thesis-Abstract en_US
dc.identifier.faculty Engineering en_US
dc.identifier.degree MSc In Construction Project Management en_US
dc.identifier.department Department of Civil Engineering en_US
dc.date.accept 2022
dc.identifier.accno TH4984 en_US


Files in this item

This item appears in the following Collection(s)

Show simple item record